Sangli 24x7 Water Project
image 1
image 2
 click to view larger picture
 

PROJECT DETAILS

  • Rehabilitation , upgradation & operation of existing distribution network of Sangli, Miraj and Kupwad Municipal Corporation
  • Project Duration: 15 months
  • Scope of Work:
    • Design of 24X7 systems for 5000 Nos. connection
    • Preparation of hydraulic model of distribution system of a city including demand assessment by using WATER GEMS
    • Updating of network map and assessment of present condition of the network
    • Procurement of Portable water meter and Flow meters for measuring equitable distribution of water in SMKMC city
    • Designing of remote monitoring terminal for pressure and flow monitoring
Pune WTP Project
image 1
image 2
 click to view larger picture
 

PROJECT DETAILS

  • Project Scope:
    • Water Treatment Plant of 125 MLD
    • Raw Water Pumping Station
    • Water Reclamation and Recycling Plant for Dirty Backwash water of Filter & Clariflocculator sludge from New & Existing Water
    • Treatment Plant
    • Augmentation & Automation of Existing Raw Water Pumping Station & Existing 125 MLD Water Treatment Plant
  • Start Date :- August 2014
  • Completion Date :- Under Execution
  • Developed for Pune Municipal Corporation
Vasai Virar Water Supply Project
image 1
image 2
 click to view larger picture
 

PROJECT DETAILS

  • Project Scope :
    • RCC Jackwell and overhead pump house
    • 140 MLD Water treatment plant
    • 4.6 Kms of Raw Water Rising Main
    • 28 Kms of Pure Water Rising Main
    • 6 Nos. 300 HP Raw water pumps
    • 6 Nos. 450 HP Pure water pumps
  • Start Date :- March 2014
  • Completion Date :- Under Execution
  • Developed for Vasai Virar Municipal Corporation under Maharashtra Suvarna Jayanti Nagarotthan Mahaabhiyan
Diu Water Supply Project
image 1
image 2
image 3
 click to view larger picture
 

PROJECT DETAILS

  • Project Scope :
    • 7 Nos of Elevated Service Reservoir : 1.5- 7 ML
    • 4 Nos of Sump
    • 8 MLD Water Treatment Plant
    • Pure Water Pumping Station- 3 Nos,
    • Raw Water Transmission Main : 18.12 Kms
    • Pure Water Pumping Main : 19.78 Kms
    • DI K-7 Distribution Network : 32.86 Kms
    • HDPE Pipe Network : 8.40 Kms
  • Start Date :- June 2013
  • Completion Date :- Under Execution
  • Developed for OMNIBUS INDUSTRIAL DEVP. CORP under Water Supply Scheme based on Sardar Sarovar Canal Based Pipeline project for Diu district.

Tatva’s Water Treatment, Supply & Distribution Projects
Tatva’s Water Treatment, Supply & Distribution Projects

Some of the projects that Tatva has undertaken in relation with water treatment, supply and distribution are:

  • 324 MLD water treatment plant (WTP) at Ambernath
  • 150 MLD WTP at Pen
  • 4 MLD non-conventional WTP at Chakan
  • 3.6 MLD non-conventional WTP at Ashti
  • 2800 m3 elevated service reservoir at Sector 29, Navi Mumbai
  • 2600 m3 elevated service reservoir at Warje, Pune
  • Weir at Alandi across river Indrayani for PWD Pune
  • 900 mm dia. M.S. pipeline from Century Enka to Bhosari for MIDC
  • AC Pressure Pipeline varying from 80 to 350 mm dia. 72 Kms. in length for Buldhana RRWSS
  • PVC Pipeline 63mm to 140mm Dia. 68 Kms. at Pune
  • Regional Rural Water Supply Scheme for 22 villages in BULDHANA district for MJP under World Bank Aid
  • Regional Rural Water Supply Scheme for Mangrulpir, Dist. Washim

In order to ensure timely provision of water to all sources, water supply management processes have been implemented by Tatva at the aforementioned plants. Water supply is an issue that continues to grow in importance. As water is essential to life, at Tatva we believe in ensuring that distribution of all treated water is carried out efficiently.



SolidWasteManagement

Solid waste can broadly be classified into two categories.

Wastewater Management

Urban water supply and sanitation are important basic needs ...

Waste-to-Energy

Waste-to-energy or energy-from-waste is the process ...